  1. Subject: big cowboy - additional production
  2. tom did some footwork and questioning and determined where the additional big cowboy production is coming from . apparently , hpl cut a deal to purchase this gas at " hpl meters " at rocher and big cowboy # 2 , so the gas had been pathed on the gathering agreement into our pipe . all along , these volumes have been flowing into the gepl / big cowboy system and on to king ranch . tom and i spoke with clem about the most correct way to reflect the physical and determined that a transport usage ticket needed to be put into place , as im wellhead , to transfer the volumes from hpl to gepl and into the plant .
  3. we unpathed the gathering agreement and brokered the hpl purchase to the tu tickets and moved the gas on our transport on gepl to the plant , effective april 1 . this resolves our overproduction issues for april and forward .
  4. please let me know if you have any further questions , comments , or information to add .
  5. mary