- Subject: texoma - beaumont hpl maintenance
- this is in regard to the maintenance that you want to do at the texoma -
- beaumont interconnect ( replace some valves , i believe ) .
- we had discussed doing this at a time when mobil beaumont refinery would have
- low gas takes . that window of opportunity will be in early to mid february .
- mobil will take down some of the units at different times during the month .
- some of these units are endothermic , some are exothermic , so in some cases
- their gas load goes up when they take certain units down . but based on the
- schedule of ups and downs that i ' ve been given , it looks like their gas load
- will be at a low point between february 1 and february 12 , at somewhere
- around 50 , 000 / d . last we talked about hpl continuing to deliver 20 , 000 / d
- through the low pressure meter , and delivering the rest through centana . is
- this still the plan ? ?
- we met with mobil last year in july to talk to them about what we need to
- do : that it would take less than a day , and that during that time , hpl would
- deliver some of our gas to them through the centana meter . but that meeting
- was a long time ago , and we might need to meet again - you know how
- conservative
- one thing of concern : in the past two months , we have effected some of our
- midcon delivery obligation by delivering 30 , 000 / d gas in kind to mobil
- beaumont . so we will not be able to do this during the day that we do our
- maintenance .
- once you gents let me know what you game plan is and confirm how we ' ll handle
- gas flows while we do our work , i ' d like to be the one that initially tells
- mobil of our plans and set up the initial meeting . it ' s going to take a lot
- of coordination because i can guarantee you that mobil ' s maintenance schedule
- will change !
- lee