2954.2000-11-27.farmer.ham.txt 1.5 KB

12345678910111213141516171819202122232425
  1. Subject: natural gas nomination for december 2000 - - r e v i s i o n
  2. please revise the natural gas nomination for the mtbe plant for december 2000
  3. as follows :
  4. 10 , 000 mmbtu for the first 15 days of the month
  5. 2 , 000 mmbut for the last half of the month
  6. - - - - - - - - - - - - - - - - - - - - - - forwarded by maritta mullet / gpgfin / enron on 11 / 27 / 2000
  7. 05 : 01 pm - - - - - - - - - - - - - - - - - - - - - - - - - - -
  8. maritta mullet
  9. 11 / 27 / 2000 04 : 44 pm
  10. to : david bush / ecf / enron @ enron , mark diedrich / gpgfin / enron @ enron , steven m
  11. elliott / hou / ect @ ect , daren j farmer / hou / ect @ ect , paul fox / ecf / enron @ enron ,
  12. david m johnson / ecf / enron @ enron , robert e lee / hou / ect @ ect , anita
  13. luong / hou / ect @ ect , gregg lenart / hou / ect @ ect , thomas meers / gpgfin / enron @ enron ,
  14. michael mitcham / gpgfin / enron @ enron , john l nowlan / hou / ect @ ect , lee l
  15. papayoti / hou / ect @ ect , james prentice / gpgfin / enron @ enron , kerry
  16. roper / gpgfin / enron @ enron , sally shuler / gpgfin / enron @ enron
  17. cc :
  18. subject : natural gas nomination for december 2000
  19. enron methanol nominates the following natural gas requirements for the
  20. methanol plant for december 2000 :
  21. 33 , 000 mmbtu per day
  22. egpfc nominates the following natural gas requirements for the mtbe plant at
  23. morgan ' s point for december 2000 :
  24. 12 , 000 mmbtu per day for the first 15 days of the month . none for the last
  25. half of the month . mtbe plant will be down after december 15 .