  1. Subject: tetco / hpl ( enerfin ) meter # 986892
  2. step i .
  3. romeo : please do step 1 today , 10 / 4 / 00 .
  4. 1 . please change the confirmed noms to zero for all contracts that have be
  5. nominated for period 1 / 1 / 00 thru 10 / 31 / 00 for the above meter .
  6. 2 . change the allocation method to " not allocatable " effective 1 / 1 / 99 .
  7. 3 . please reallocate the meter for period 1 / 1 / 99 thru 10 / 31 / 00 .
  8. 4 . call me after the above tasks have been completed .
  9. step ii .
  10. sherlyn : please check the following tommorrow , 10 / 5 / 00 .
  11. 1 verify with settlements that the zero bav adjustment were received for
  12. all contract activities at meter 986892 for period 1 / 1 / 99 thru 9 / 30 / 00 .
  13. 2 . after verification is complete , please call me .
  14. step iii .
  15. donna : i will call you tomorrow , 10 / 5 / 00 to inform when you can make the
  16. following changes :
  17. 1 . change the meter # and drn # at facility # 501026 . this facility should
  18. be trade and nom " yes " .
  19. 2 . change the meter # and drn # at facility # 515136 . this facility should
  20. be trade and nom " no " .
  21. 3 . after completion , please call me as well as romeo ( x - 34544 ) .
  22. step iv .
  23. romeo : upon receiving a call from donna :
  24. 1 . please make the appropriate changes or corrections in pops system for the
  25. facility changes made by global facilities dept . my understanding is that
  26. these changes can not be done automatically .
  27. 2 . upon completion , please call me .
  28. step v .
  29. jackie :
  30. 1 . tomorrow , 10 / 05 / 00 , after i am informed that romeo has made his changes ,
  31. i will let you know and you may begin scheduling meter # 0980439 which is the
  32. meter replacing # 0986892 .
  33. 2 . after completion , please let me know .
  34. * * * * * * * *
  35. gary :
  36. this could create some problems for gas control , because all confirmed
  37. volumes will be zeroed including october , 2000 activities at meter 986892
  38. today ( 10 / 4 / 00 ) . this should correct itself within 24 thru 48 hours at
  39. meter # 980439 .
  40. daren :
  41. this could also create some issues for you , but remember , these issues should
  42. clear within 24 to 48 hours .
  43. victor :
  44. this is just for your information , since this should not create and changes
  45. for you .