- Subject: baytown 12 ' ' pigging affected meters
- cheryl
- please make sure letters are sent out this week for the baytown 12 " pigging
- project . all producers are to be shut - in by 9 : 00 am on september 12 , 2000 .
- the outage is expected to last three to four days .
- if you have any questions please call me 36449
- gary hanks
- - - - - - - - - - - - - - - - - - - - - - - forwarded by gary a hanks / hou / ect on 08 / 29 / 2000 04 : 17
- pm - - - - - - - - - - - - - - - - - - - - - - - - - - -
- enron north america corp .
- from : gary a hanks 08 / 11 / 2000 11 : 13 am
- to : cheryl dudley / hou / ect @ ect , daren j farmer / hou / ect @ ect , pat
- clynes / corp / enron @ enron , lauri a allen / hou / ect @ ect , earl tisdale / hou / ect @ ect ,
- melissa graves / hou / ect @ ect , george weissman / hou / ect @ ect , shawna
- flynn / hou / ect @ ect
- cc : steve hpl schneider / hou / ect @ ect , james mckay / hou / ect @ ect , jeffrey a
- austin / hou / ect @ ect , william d cosby / gco / enron @ enron
- subject : baytown 12 ' ' pigging affected meters
- the baytown 12 " pigging project scheduled for august 15 has been cancelled .
- the work has been rescheduled and is expected to begin september 12 . the
- same list of meters will be shut - in early on the morning of september 12 and
- remain shut - in approximately three to four days .
- if you have any questions please call me 36449 .
- thanks
- gary hanks
- - - - - - - - - - - - - - - - - - - - - - - forwarded by gary a hanks / hou / ect on 08 / 08 / 2000 12 : 49
- pm - - - - - - - - - - - - - - - - - - - - - - - - - - -
- enron north america corp .
- from : gary a hanks 08 / 01 / 2000 10 : 55 am
- to : cheryl dudley / hou / ect @ ect , daren j farmer / hou / ect @ ect , pat
- clynes / corp / enron @ enron , lauri a allen / hou / ect @ ect , earl tisdale / hou / ect @ ect ,
- melissa graves / hou / ect @ ect , george weissman / hou / ect @ ect , shawna
- flynn / hou / ect @ ect
- cc : steve hpl schneider / hou / ect @ ect , james mckay / hou / ect @ ect , jeffrey a
- austin / hou / ect @ ect
- subject : baytown 12 ' ' pigging affected meters
- the meters listed in the attached email will be shut - in in order to pig the
- baytown 12 " . the meters will be shut - in early on the morning of august 15 ,
- and remain shut - in for approximately five to ten days .
- if you have any questions please call me 36449 .
- thanks
- gary hanks
- mgr gas control
- - - - - - - - - - - - - - - - - - - - - - - forwarded by gary a hanks / hou / ect on 08 / 01 / 2000 10 : 44
- am - - - - - - - - - - - - - - - - - - - - - - - - - - -
- mike vollmering @ enron
- 08 / 01 / 2000 08 : 59 am
- to : gary a hanks / hou / ect @ ect , jill t zivley / hou / ect @ ect
- cc : james mckay / hou / ect @ ect , pat flavin / gco / enron @ enron , liberty team
- hpl / gco / enron @ enron
- subject : baytown 12 ' '
- the columbus energy wiggins # 1 ( 989634 ) will be effected by the pigging
- project . the tap valve is installed in the mlv bypass and the bypass will be
- removed to blow down the line .
- here is a list of all the producers that will be effected .
- columbus energy - - - - - - - - wiggins # 1 ( 989634 ) and fig orchard ( 986764 )
- sanchez o mike
|