Subject: texoma - beaumont interconnect mobil says the low point of their takes will be during february will be from feb 1 to 14 . so any day in that time period would be a good time for hpl to do the required maintenance at the texoma - beaumont system interconnect . we need to define our game plan : - what day to do the work - how much gas hpl will deliver through our own meter - how we use centana to deliver the rest of the hpl volumes - if we had planned in feb to baseload some of our midcon obligation at mobil as we have done in dec and jan , then we will need to do something different whenever we do the maintenance james - we are scheduled to meet with mobil in beaumont at 10 . 30 am thursday feb 1 , to go over the game plan with them . pat - do you want anyone from hms to attend ? thanks lee